October 2000 Images
Images below are 10% of the original size. Click on an image to see the image at 25% of the original size. 100% size images would take up too much room to put on this server. After clicking on an image, click on the "back" button on your browser to return to this page. If you want a larger picture of any of the images, contact the .
13 October 2000 Pile driving for the bridge pillar foundation nearing completion on the east side of the Pic River. |
|
While the piles are being driven for the east side of the bridge, preparations are being made on the west side of the bridge for pile driving. |
|
14 October 2000 Pile driving is finished on the east side of the river. Concrete work starts soon. |
|
Pile driver is on the west side of the river and almost ready to go. |
|
16 October 2000 The east side of the river is being prepared for concrete. Pillar foundation formed up and the hole is being dug for the counterweight. |
|
Pile driving on the west side of the river is nearing completion. |
|
Close up of the pile driving. |
|
18 October 2000 The foundation for the east pillars just received it's last load of concrete. |
|
27 October 2000 East side pillar concrete almost finished. One more load required for the north (left) pillar. You can see the concrete for the counterweight behind the excavator. |
|
Close up of the east side pillars. |
|
Close up of the concrete for the counterweight on the east side of the Pic River. |
Last updated 11 December 2001.